Mid November Update

Project Updates

  • Fire and sprinkler system being installed.
  • Flooring in in stock and scheduled to be installed on 11/21.
  • Drywall ceiling for back of the kitchen completed today.
  • FRP down hallway to outside installed Monday.
  • Steel Panels being installed- dishwasher area complete.
  • Bumper guards and stainless corner guards are in stock.
  • Back Stairs well second story landing has been poured – stair well is in stock.
  • Metal roof will be completed in next 2 weeks.