December Updates – Images Gallery
The Equipment is in, check and compare the Before (orange tails) and After. Before Before Before Before After After After After
Venice Yacht Club 2022 Project website.
Please use the following list to read the updates.
The Equipment is in, check and compare the Before (orange tails) and After. Before Before Before Before After After After After
Project Updates Fire and sprinkler system being installed. Flooring in in stock and scheduled to be installed on 11/21. Drywall
External Stairwell columns have been stood, and the back patio will be poured next week. The Sprinklers will be installed
The roof: We are one Hurricane behind (about two weeks) and are currently removing the old roof.Delays on mainline stainless
We lost a week on our roof replacement due to the storm. Demolition will begin next week. Framing has started